§ 23-51. Restoration, etc.  


Latest version.
  • (a)

    All temporary and permanent repairs to excavated areas in streets or other public property, including filling, compacting, and resurfacing shall be made, or contracted for by the city in a manner prescribed by the city engineer, and an accurate account of costs thereof shall be kept.

    (b)

    Within sixty (60) days following the completion of such permanent repairs, the city engineer shall determine actual costs of repairs, including cost of investigation, and prepare and furnish to such permit holder an itemized statement thereof and claim additional payment from, or make refund to, the permit holder, as the cost may be.

    (c)

    In lieu of above provisions relating to cost and cost adjustment for street openings, the city may charge on the basis of surface square feet removed, excavated cubic feet, or a combination of surface square feet and excavated cubic feet, on an established unit price uniformly charged.